Day 1 Timings

Over the two day event, All-Energy will host a series of 1-2-1 ‘speed dating’ meetings in the showfloor meet the developer lounge. It’s where you can literally ‘Meet the Developers’ looking to expand their supply chains; and also seek 1-2-1 advice from companies offering to share their experiences so you can mirror their latest achievement. We have a range of owner/operators of energy projects and devices looking to work with you so check out the times they are available below; 

Wednesday 11th May

13:00-15:00 EDF Renewables – David Sweenie, Development Manager

David will be representing Neart na Gaoithe and EDF Renewables and keen to hear from organisations interested in all aspects of development, construction and operation of offshore wind deployment


11:00-12:45 & 13:00-15:00 VerdErg – Lars Boerner, CEO

VerdErg Renewable Energy is the developer of “VETT”, a novel low-head hydropower technology. VETT uses venturi principles to amplify the pressure differential across standard turbines for use in low-head settings, reducing turbine size by up to 5x. The arrangement is novel but components used are conventional. VerdErg is looking to meet companies in the following fields: Hydro project developers, hydro consultants, small Kaplan/Propeller turbines (300-600mm), permanent magnet generators (submerged and dry), submersible enclosures, GRP pipe manufacturing (straight and conical), chain and belt drives, bearings, gates and valves. 


13:00-15:00 & 15:45-17:30 Corio Generation – Benoit Lavinal, Head of Procurement

We have a project pipeline of over 15 GW. Our global team of offshore wind specialists take projects from origination, through development and construction, and into operations.


11:00-12:45 & 15:45-17:30 Red Rock Power, Inch Cape Offshore Wind Farm – Rob Lilly, Supply Chain Specialist

The Inch Cape Offshore Wind Farm, owned by Red Rock Power and ESB, will see up to 72 turbines located 15 km off the Angus Coast and connect to the National Grid at Cockenzie, East Lothian. For more information visit https://www.inchcapewind.com/supply-chain/ - Eager to engage with innovative O&M, fabrication, foundation installation/noise mitigation and SCADA 


13:00-15:00 & 15:45-17:30 Red Rock Power, Benbrack Onshore Wind Farm – Andrew Pringle, Construction Manager

Benbrack Onshore Wind Farm owned by Red Rock Power, is located in Dumfries & Galloway. The late-stage development is preparing to commence onsite works in Summer 2022. For more information visit https://www.redrockpower.co.uk/benbrack/supply-chain-opportunities/ - Eager to engage with Electrical contractors, building contractors, communications, local plant hire, raw materials 


13:00-15:00 Floating Energy Allyance - Alasdair MacLeod, Project Director

Floating Energy Allyance is the developer of a major floating wind project of around 960MW, which is sited 75km off the northeast coast of Scotland.  The partnership secured the option agreement for the NE8 area in the ScotWind leasing round. The partnership, consisting of BayWa r.e., Elicio NV, and BW Ideol, brings together highly significant, relevant and complementary expertise, and is committed to local manufacture of the project’s concrete foundations and to maximising other opportunities for the Scottish and UK supply chains.


11:00-12:45 ScottishPower, Kirsty Adams, Senior Supply Chain Strategy Manager

Join Kirsty to discuss different projects across ScottishPower including MachairWind, MarramWind, CampionWind and more. Looking to engage with the following suppliers:

  • Foundation/floating technology providers
  • Vessel providers/Transport & installation specialists for offshore wind
  • Substation providers (onshore and offshore)
  • Cable manufacturers
  • Geotech/geophys/geoscience surveyors

15:45 – 17:30 EnbW - Duncan Ayling, Supply Manager, UK Offshore Wind

Morgan and Morna are two wind farms being developed by BP and EnBW in the Irish Sea. They are Located approximately 30km from the coast, with a combined area of approximately 800 km2. Morven is located in the North Sea approximately 60km from the coast of Aberdeen with an area of aproximately 860km2.  The combined potential generating capacity of 5.9 GW is sufficient to power the equivalent of around 6 million UK households with clean electricity. Eager to engage with local Scottish suppliers: ports, vessels, fabrication yards (primary foundation steel and secondary steel), HVAC & HVDC cables 


11:00-12:45 & 15:45-17:30 Cierco - Alex Gauntt, Supply Chain Director

Cierco is an independent renewable energy project development company established in 2001 with a simple goal - to engage in the field of offshore wind power and to drive technologies and projects to reach cost levels competitive with those of conventional power. Cierco, as part of the Joint Venture together with SBM named ‘Floventis’, is developing the 2 x 100 MW Llŷr floating wind farms in the Celtic Sea, as well as the CADEMO floating wind project off the Californian West Coast USA. Cierco is also developing the Forthwind offshore wind project in Scotland. All projects are expected to be operational before 2030. 

Alex Gauntt is Supply Chain Director for the Cierco including Floventis Project portfolio, responsible for developing the supply chain strategy and plan to deliver best value options and opportunities to the company. Eager to engage with: 

  • Owner’s Engineer companies 
  • Electrical consultants 
  • U.S. based survey companies
  • Floating foundation technology providers
  • Condition monitoring solution providers
  • (Onshore) heavy lifting companies
  • EPC companies
  • Wind turbine OEMs
  • Harbour engineering contractors/designers
  • Marine insurance and risk consultants

11:00-12:45 Simply Blue Group - Erik Kiltie, Deputy Technical Manager, Salamander Floating Wind

Salamander is a 100 MW stepping-stone floating wind project off the east coast of Scotland. It is designed to provide the Scottish supply chain with an early capacity development opportunity before larger ScotWind projects kick off. Salamander is being developed by Simply Blue Group in collaboration with majority stakeholder Ørsted and JV partner Subsea 7

13:00-15:00 Ocean Winds - Andrew Hamilton, Development Manager – Caledonia Offshore Windfarm

Ocean Winds were awarded the rights to develop the NE4 Plan Option Area through the Scottish Governments ScotWind leasing process in January 2022.  The 440km2 site sits in the outer Moray Firth in the North of Scotland, immediately adjacent to the north-eastern boundary of the Moray East Offshore Windfarm and has been named by OW as The Caledonia Offshore Wind Farm

TO REQUEST MEETING(S):

If you are interested in booking a meeting with any of our developers please send an email with the following information to Carlos Fernandes carlos.fernandes@rxglobal.com             

Please ensure you provide the following information: 

*the times the developers are available are indicated already so you will need to ensure you are free for their entire timeslot before you are allocated a more precise time 

NB: meetings are confirmed at the developers' discretion and dependent on level of demand, an exact time will be confirmed with a member of our team once all the above has been approved.